The Situation![]()
EnergySource LLC had a 30-year PPA with a utility off-taker for a utility-scale geothermal power plant, but lacked the capital required for construction.
The Problem![]()
The Project Finance market had not seen a triple-flash geothermal transaction in 20 years and to make matters worse, there was no EPC wrap on the project.
The SolutionHannon Armstrong advised EnergySource how to create a synthetic EPC structure and reacquainted the lenders on the merits of base-load geothermal power plants. As a result, Hannon Armstrong was successful in arranging approximately $400 million in construction loans and project equity for the company. |
The Benefit![]()
EnergySource was able to begin construction of its geothermal power plant, bringing hundreds of jobs to Imperial County, CA, and was able to finance the development of its project portfolio.